ZUBA Plaza14 to 17
Three residential towers and a corporate tower with coworking and offices.
14–17ZUBA buildings
Greater AsunciónCity
Under constructionProgress as of 31/10/2026
47.8 %Construction progress






Construction progress
Construction update
ZUBA publishes a monthly report with photos and percentages. This is the latest one, as of October 31, 2026.
Corporate Tower
Report as of 31/10/2026
46.5%
- Rooftop slab (level 10) poured
- Masonry up to level 8



Tower 1
Report as of 31/10/2026
47.8%
- Columns from level 14 to rooftop
- Flooring installed up to level 5



Tower 2
Report as of 31/10/2026
37.9%
- Level 12 slab poured
- Masonry on level 8



Tower 3
Report as of 31/10/2026
34.5%
- Columns, levels 10–11
- Masonry up to level 8