Under constructionProgress as of 31/10/2026
93 %Construction progress




Construction progress
Construction update
ZUBA publishes a monthly report with photos and percentages. This is the latest one, as of October 31, 2026.
ZUBA 19
Report as of 31/10/2026
93%
- Masonry: 99.86 %
- Kitchen cabinets: 98 %
- Painting: 66.34 %